How to change the completion date and time

How to change the completion date and time

Postby dgtale » Wed 19. Sep 2012, 20:31

When you check off a task it takes the current time as completion time.
Follow the actions depicted below to change the completion time if you need to.

snap1.png
snap1.png (35.54 KiB) Viewed 6440 times

snap2.png
snap2.png (19.49 KiB) Viewed 6440 times
dgtale
Administrator
 
Posts: 508
Joined: Sat 21. May 2011, 14:03